INSTALLATION NOTES
1. CS-4111
- CUT 2" WIDE x ("X" MINUS 4") RECTANGULAR
OPENING IN DUCT AT DESIRED LOCATION.
CS-4116
- CUT 3" WIDE x ("X" MINUS 4") RECTANGULAR
OPENING DUCT AT DESIRED LOCATION.
2. APPLY
BEAD OF BUTYL RUBBER CAULK OR EQUAL AROUND OPENING IF DESIRED.
3. INSERT
DISTRIBUTION TUBES IN OPENING WITH CONDENSATE PORT FACING "DOWN".
INSTALL HEADER SO THAT IT IS PLUMB OR HAS A MAXIMUM SLOPE OF
1/16" PER FOOT TOWARDS DRAIN.
4. FASTEN
SUPPLY HEADER TO DUCTWORK WITH (6) CS-163 DRILL QUIKS (INCLUDED)
AND THREADED ROD AS SHOWN. THREADED ROD MUST SUPPORT UNIT WEIGHT.
USE DRILL QUIKS FOR LOCATING ONLY.
5. APPROXIMATE
UNIT WEIGHT (IN LBS.) CS-4111 = (4.64 x HEADER LENGTH [IN FEET])
+ (0.93 x LENGTH OF DISTRIBUTION TUBE [IN FEET]) + (0.93 x LENGTH
OF DISTRIBUTION TUBE [IN FEET] x NUMBER OF TUBES)
CS-4116 = (6.28 x HEADER LENGTH [IN FEET] + (1.70 x LENGTH OF
DISTRIBUTION TUBE [IN FEET] x NUMBER OF TUBES)
6. CONSULT
FACTORY IF OTHER MOUNTING ARRANGEMENTS ARE NECESSARY.